Rzeszów, Poland · Under construction

Luxury apartments for rent in the centre of Rzeszów

An RS Holding investment at ul. Dąbrówki 8 in Rzeszów, Poland. The extension and vertical expansion of the existing office building turn it into an apartment building for short-term rental. Completion is scheduled for December 2027.

Company

A good address for short-term rental

RS Holding is the investor behind the extension of its own building at ul. Dąbrówki 8 in Rzeszów. The apartments remain our own and are intended for short-term rental. The building stays with us for years, so we choose materials and workmanship with durability and running costs in mind.

We are right in the centre of Rzeszów. In the neighbourhood: a park, a school and nurseries, shops and restaurants within walking distance. The stadium is close by, and the Pratt & Whitney plant a few minutes away by car.

Company registration details

Legal entity
RSHolding Sp. z o.o. Sp. K.
Registered office
ul. Dąbrówki 8, 35-036 Rzeszów
NIP
8133809791
KRS
0000780671
REGON
383029426

One investment, one address in central Rzeszów.

Investment

Dąbrówki, Rzeszów

Extension, reconstruction and vertical expansion of the existing office building at ul. Dąbrówki 8, with a change of use to a multi-family residential building, together with a new adjoining part with two levels of parking.

30
Apartments
6
Floors
34 to 72 m²
Apartment floor areas
Dec 2027
Completion
Schedule

Construction stages

As of August 2026

  1. Concept design · 2024 · completed Architectural concept and project documentation
  2. Building design · 2025 · completed Building design and obtaining permits
  3. Stage I · 2025 · in progress Extension, reconstruction and two-storey vertical expansion of the existing building
  4. Stage II · planned Construction of a new adjoining part on the neighbouring plot: two levels of parking, with the remaining floors given over to apartments
Work in progress

From the site

Current state of works at ul. Dąbrówki 8 in Rzeszów: a steel-framed storey being added and façade works on the existing building.

Façade of the existing building under works, with scaffolding, a crane and packs of insulation material in the foreground
Steel frame of the storey being added, with profiled floor decking in place
The construction site seen from the entrance gate, numbered 8

Photographs taken 7 August 2026

Contact

Suppliers and tender enquiries

As the investor, we work continuously with material suppliers and contractors. Construction runs until the end of 2027 across two construction stages. For quotations, please get in touch directly.

Administration

Anna Paszkowska

anna@rsholding.com.pl +48 793 738 362
Investor

Robert Supulak

rs@rsholding.com.pl +48 793 738 360